Process Equipment & Plant Design Mcqs for Chemical


Q.  The operating velocity in the absorption tower is usually 40-50% of the flooding velocity. Packed absorption towers are normally designed for a pressure drop of about _________________ mm of water column per metre height of packing?

a. 1-5
b. 20-40
c. 100-150
d. 1000-1500



 
 