Q.  The correct sequence of these operations in tunnel construction is______________?
Consider the following operations :
1. Drilling
2. Blasting
3. Mucking
4. Placing steel
5. Placing concrete


a. 1,2,4,3,5
b. 1,3,2,4,5
c. 1,2,3,4,5
d. 1,3,4,2,5



 
 