Q.  Pick up the correct statement regarding the centre line method of estimating a building?

a. Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item
b. The centre line is worked out separately for different sections of walls of a building
c. The centre line length is reduced by half the layer of main wall joining the partition wall
d. All the above



 
 