Q. P is able to do a piece of work in 15 days and Q can do the same work in 20 days. If they can work together for 4 days, what is the fraction of work left?
a. 8/15
b. 7/15
c. 11/15
d. 2/11
Amount of work P can do in 1 day = 1/15
Amount of work Q can do in 1 day = 1/20
Amount of work P and Q can do in 1 day = 1/15 + 1/20 = 7/60
Amount of work P and Q can together do in 4 days = 4 × (7/60) = 7/15
Fraction of work left = 1 – 7/15= 8/15
Related Content
- Any line segment can be formed by joinin...
- A total of 3000 chocolates were distribu...
- By expressing the cos 82° in terms of t...
- 24 – [2.4 – {0.24 * 2 – (0.024 –...
- Hazel borrowed $250000 for 7 years at in...
- HCF of 3/16, 5/12, 7/8 is__________?
- The elements in set {Vowels in the word ...
- Rs.1200 divided among P, Q and R. P gets...
- A sum of money place at compound interes...
- If two pipes function together, the cist...
- The probability of getting a red ace if ...
- 25% of 30% of 45% is equal to__________?
- P can do a work in the same time in whic...
- A man purchased 3 blankets @ Rs.100 each...
- The tan P of triangle PQR with respect t...
- In the formula 2πr, the 'r' is consider...
- The cost price of 13 articles is equal t...
- A typist uses a paper 30 cm by 15 cm. He...
- P, Q and R can complete a work in 24, 6 ...
- A group of people has provisions for 29 ...
- In the triangle ABC, if angle A = 89°, ...
- Rs. 20 is the true discount on Rs. 260 d...
- A batsman in his 17th innings makes a sc...
- By solving the inequality 1⁄4(2 - x) >...
- (0.9 * 0.9 – 0.8 * 0.8)/1.7 = ________...
- A scale of map is 1cm to 5km, the distan...
- A can complete a work in 12 days with a ...
- The ratio of boys and girls in a class w...
- The average of five numbers is 27. If on...
- The average age of 15 students of a clas...