Q.  P can lay railway track between two stations in 16 days. Q can do the same job in 12 days. With the help of R, they completes the job in 4 days. How much days does it take for R alone to complete the work?

a. 9(3/5) days
b. 9(1/5) days
c. 9(2/5) days
d. 10 days



 
 