Q. If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be__________________?
a. 2.3% and 84.1%
b. 97.7% and 84.1%
c. 97.7 % and 15.9%
d. 15.9% and 97.7%