Construction Planning & Management Mcqs


Q.  Free float is mainly used to_________________?

a. identify the activities which can be delayed without affecting the total float of preceding activity
b. identify the activities, which can be delayed without affecting the total float of succeeding activity
c. establish priorities
d. identify the activities which can be delayed without affecting the total float of either the preceding or succeeding activities



 
 