Q.  An optimum project schedule implies_______________?

a. optimum utilization of men, machines and materials
b. lowest possible cost and shortest possible time for project
c. timely execution of project
d. to produce best results under given constraints
e. realistic execution time, minimum cost and maximum profits



 
 