Software Engineering Questions - Set 9

1)   Grouping of all functionally related elements is known as ______ .

a. Cohesion
b. Coupling
c. Both A & B
d. None of the above
Answer  Explanation 

ANSWER: Cohesion

Explanation:
No explanation is available for this question!


2)   CASE tools are used by software project managers, analysts and engineers to develop software system.

a. True
b. False
Answer  Explanation 

ANSWER: True

Explanation:
No explanation is available for this question!


3)   The scope of CASE tools goes throughout the SDLC.

a. Yes
b. No
Answer  Explanation 

ANSWER: Yes

Explanation:
No explanation is available for this question!


4)   Which type of DFD concentrates on the system process and flow of data in the system?

a. Logical DFD
b. Physical DFD
c. Both A & B
d. None of the above
Answer  Explanation 

ANSWER: Logical DFD

Explanation:
No explanation is available for this question!


5)   Every attribute is defined by its corresponding set of values is called ______ .

a. Entity
b. Domain
c. Relationship
d. None of the above
Answer  Explanation 

ANSWER: Domain

Explanation:
No explanation is available for this question!


6)   Building an excellent product or system that no one really want a risk is a ________ .

a. Technical risk
b. Schedule risk
c. Business risk
d. Performance risk
Answer  Explanation 

ANSWER: Business risk

Explanation:
No explanation is available for this question!


7)   Budget is not a section in the standard SQA plans that are recommended in IEEE.

a. True
b. False
Answer  Explanation 

ANSWER: True

Explanation:
No explanation is available for this question!


8)   In the management subsystem what is the functional elements and associated workflow will support the content object identification, version control, change management, change auditing and reporting?

a. Content database
b. Database capabilities
c. Configuration management function
d. All mentioned above
Answer  Explanation 

ANSWER: Configuration management function

Explanation:
No explanation is available for this question!


9)   Abbreviate the term ILFs.

a. Interface logical files
b. Internal logical files
c. Input logical files
d. Internal logical function
Answer  Explanation 

ANSWER: Internal logical files

Explanation:
No explanation is available for this question!


10)   What is a special set of ISO guidelines that developed to help the interpret standard for the use in software process?

a. ISO 9001-2000
b. ISO 9001-2001
c. ISO 9000-3
d. ISO 9000-4
Answer  Explanation 

ANSWER: ISO 9000-3

Explanation:
No explanation is available for this question!


11)   The ability to encourage the technical people to produce their best ability is known as ______ .

a. Organization
b. Motivation
c. Ideas or innovation
d. None of the above
Answer  Explanation 

ANSWER: Motivation

Explanation:
No explanation is available for this question!


12)   Mechanics for refining the processing tasks that are required for software to accomplish in some desired function is ______ .

a. Process decomposition
b. Problem decomposition
c. Functional decomposition
d. None of the above
Answer  Explanation 

ANSWER: Functional decomposition

Explanation:
No explanation is available for this question!


13)   Design phase is followed by ______ .

a. Coding
b. Testing
c. Maintenance
d. None of the above.
Answer  Explanation 

ANSWER: Coding

Explanation:
No explanation is available for this question!


14)   In software maintenance tackling the changes in the hardware and software environment where the software works, is called ______ .

a. Corrective
b. Perfective
c. Adaptive
d. Preventive
Answer  Explanation 

ANSWER: Adaptive

Explanation:
No explanation is available for this question!


15)   From the following which quality deals with maintaining the quality of the software product?

a. Quality assurance
b. Quality control
c. Quality efficiency
d. None of the above
Answer  Explanation 

ANSWER: Quality control

Explanation:
No explanation is available for this question!


16)   Function-oriented design is comprised of many smaller sub-systems is known as, Functions.

a. Yes
b. No
Answer  Explanation 

ANSWER: Yes

Explanation:
No explanation is available for this question!


17)   State if the followings are true or false. For scheduling a project, it is necessary to: 1) Break down the project tasks into smaller, manageable form. 2) Find out various tasks and correlate them. 3) Estimate time frame required for each task. 4) Divide time into work-units.

a. True
b. False
Answer  Explanation 

ANSWER: True

Explanation:
No explanation is available for this question!


18)   Software project manager is engaged with software management activities. He is responsible for ______ .

a. Project planning.
b. Monitoring the progress
c. Communication among stakeholders
d. All mentioned above
e. None of the above
Answer  Explanation 

ANSWER: All mentioned above

Explanation:
No explanation is available for this question!


19)   Classes communicate with one another via ______ .

a. Read sensors
b. Dial phones
c. Messages
d. None of the above
Answer  Explanation 

ANSWER: Messages

Explanation:
No explanation is available for this question!


20)   Software is not considered to be collection of executable programming code, associated libraries and documentations.

a. True
b. False
Answer  Explanation 

ANSWER: False

Explanation:
No explanation is available for this question!