Q.  Which of the following is a project scheduling method that can be applied to software development ?

a. PERT
b. CPM
c. CMM
d. Both PERT and CPM


ANSWER: See Answer
 
Program evaluation and review technique (PERT) and critical path method (CPM) are two project scheduling methods that can be applied to software development.
MCQs:  A sequence of baselines representing different versions of a system is known as ____________________?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Which of the following is a collection of component versions that make up a system ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Which of the following is a part of system release ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Which of the following term is best defined by the statement “The creation of a new codeline from a version in an existing codeline” ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Which activity sits at the core of software requirements analysis ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  What assess the risk and your plans for risk mitigation and revise these when you learn more about the risk ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Risk management is one of the most important jobs for a__________________?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Which of the following term is best defined by the statement: “The underlying technology on which the system is built is superseded by new technology.” ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Which of the following risks are derived from the organizational environment where the software is being developed ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Which of the following term is best defined by the statement: “Derive traceability information to maximize information hiding in the design.” ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  A make-buy decision is based on whether________________?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Who suggested the four different approaches to the sizing problem ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Which of the following is not one of the five information domain characteristics of Function Point (FP) decomposition ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  v Programming language experience is a part of which factor of COCOMO cost drivers ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  PM-CMM stands for___________________?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Who defines the business issues that often have significant influence on the project ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Which of the following is not a sign that indicates that an information systems project is in jeopardy?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Which of the following is the reason that software is delivered late ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Which of the following is a collection of project coordination technique ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Commitments to unrealistic time and resource estimates may result in____________________?
Category: Software Engineering Mcqs,   Published by: teswesm