Construction Planning & Management Mcqs


Q.  Updating may result in_________________?

a. change of critical path
b. decrease of project completion time
c. increase of project completion time
d. all of the above


ANSWER: See Answer
 
No explanation is available for this question!
MCQs:  PERT is preferred for planning because of________________? Consider the following features/factors 1. Projects are of the non-repetitive type. 2. Time required need not be known. 3. Time required is known precisely. 4. Events have been established for planning. 5. Emphasis is given to activities of project
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  The correct sequence of these operations in tunnel construction is______________? Consider the following operations : 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  Which one of the following is not an excavating and moving type of equipment ?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  For excavating utility trenches with precise control of depth, the excavation equipment used is_______________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  Batching refers to________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted, and pneumatic tyremounted machines would be respectively_________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  Wheeled tractors are replacing crawler tractors because________________? Consider the following statements? 1. wheeled tractors travel faster 2. crawler tractors are more expensive 3. track parts of a crawler wear out quickly 4. crawler tractors have stick control
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  Sensitivity analysis is a study of__________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  Preliminary project report for a road project must contain___________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  The basic action involved in sheep foot rolling is_______________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  The most suitable type of equipment for compaction of cohesive soils is_________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  Grader is used mainly for___________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is__________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  The correct sequence of these activities is________________? Consider the following activities in a building construction? 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  The original cost of an equipment is Rs.10,000/-. Its salvage value at the end of its total useful life of five years is Rs. 1,000/-. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  A contractor has two options : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he______________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  Mobilization advance up to 10% of the cost of work is given to a contractor_______________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  In time-cost optimization of a project, crashing is done____________?
Category: Civil Engineering Mcqs,   Published by: teswesm