Construction Planning & Management Mcqs

Q.  The correct sequence of these operations in tunnel construction is______________?
Consider the following operations :
1. Drilling
2. Blasting
3. Mucking
4. Placing steel
5. Placing concrete


a. 1,2,4,3,5
b. 1,3,2,4,5
c. 1,2,3,4,5
d. 1,3,4,2,5


ANSWER: See Answer
 
No explanation is available for this question!
MCQs:  If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be__________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be__________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  A four wheel trac*or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be___________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  The grade resistance factor for an earth moving machine can be obtained by multiplying grade percentage by a factor approximately equal to_________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Which of the following surfaces will give highest rolling resistance for a rubber tyred vehicle?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Which one of the following surfaces will give highest coefficient of traction while using crawler track tractors?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  An excavator costs Rs. 20,00,000/- and has an estimated life of 8 years. It has no salvage value at the end of 8 years. The book value of the excavator at the end of 3 years using general double declining balance method is__________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Assertion A: For a given depth of cut, the output of a power shovel can be increased by decreasing the angle of swing Reason R: If the angle of swing is decreased, the cycle time will be decreased_______________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  For a given size of bucket, the ideal output of a dragline will be least in_______________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Which of the following earth moving machines has the shortest cycle time?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Crash project duration is obtained by summing the________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  The constraints in case of resource smoothening operation would be_______________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Slack time refers to_______________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Economic saving of time results by crashing_________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  The direct cost of a project with respect to normal time is________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  The time with which direct cost does not reduce with the increase in time is known as_________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  What estimate would you give for the variance in above problem ?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  The independent float affects only_______________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Free float for any activity is defined as the difference between__________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts