Construction Planning & Management Mcqs

Q.  The correct sequence of these activities is________________?
Consider the following activities in a building construction?
1. Concreting of roof slabs
2. Brick-jelly lime concrete terracing
3. Erection of form work for slab
4. Construction of parapet wall in terrace


a. 1,3,2,4
b. 3,1,4,2
c. 3,1,2,4
d. 1,3,4, 2


ANSWER: See Answer
 
No explanation is available for this question!
MCQs:  Economic saving of time results by crashing_________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  The direct cost of a project with respect to normal time is________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  The time with which direct cost does not reduce with the increase in time is known as_________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  What estimate would you give for the variance in above problem ?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  The independent float affects only_______________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Free float for any activity is defined as the difference between__________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Total float for any activity is defined as the difference between________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Free float is mainly used to_________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively___________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  In the network shown in Fig. (15 fig) the latest start time of an activity 4-5 is_________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Earliest finish of an activity is always_______________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  In PERT analysis, the time estimates of activities and probability of their occurrence follow_______________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  PERT technique of network analysis is mainly useful for__________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Select the correct statement_______?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Select the incorrect statement_______?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Select the incorrect statement______?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Select the incorrect statement________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  What is defined as the certificate of indebtedness of corporation usually for a period not less than 10 years and guaranteed by a mortgage on certain assets of a corporation ?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Which is NOT an essential element of an ordinary annuity ?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  What is the type of annuity that does not have a fixed time span but continues indefinitely or forever ?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts