Estimating & Costing Mcqs


Q.  Pick up the correct statement regarding the centre line method of estimating a building?

a. Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item
b. The centre line is worked out separately for different sections of walls of a building
c. The centre line length is reduced by half the layer of main wall joining the partition wall
d. All the above


ANSWER: See Answer
 
No explanation is available for this question!
MCQs:  The item of the brick structure measured in sq.m, is___________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is__________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  Anti-siphonage pipe is connected to__________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved ?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  The concrete work for the following part of the building of specified thickness is measured in square metres_______________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  The total length of a cranked bar through a distance D. at 45° in case of a beam of effective length L, is_________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  The measurement is made for stone work in square metre in case of________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  The expected out turn of 12 mm plastering with cement mortar is_______________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  Carpet area does not include the area of_________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  In case of laying gullies, siphons, intercepting traps, the cost includes_______________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  The inspection pit or chamber is a manhole provided in a base drainage system________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  The ‘centre line method’ is specially adopted for estimating_________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  The unit of measurement is per quintal for the following?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  The order of booking dimensions is________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  The correct Prismoidal formula for volume is________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended___________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  Pick up the incorrect statement regarding a master trap from the following ?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  period in a septic tank is assumed___________________? The detention
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  If B is the width of formation, d is the height of the embankment, side slope S : 1, for a highway with no transverse slope, the area of cross-section is___________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  Pick up the item of work not included in the plinth area estimate______________?
Category: Civil Engineering Mcqs,   Published by: teswesm