Construction Planning & Management Mcqs

Q.  Latest start of an activity is always________________?

a. greater than or equal to latest event time of preceding node
b. less than or equal to latest event time of preceding node
c. equal to latest event time of preceding node
d. less than latest event time of preceding node


ANSWER: See Answer
 
No explanation is available for this question!
MCQs:  An earth moving equipment costs Rs. 5,00,000/- and has an estimated life of 10 years and a salvage value of Rs. 50,000/-.What uniform annual amount must be set aside at the end of each of the 10 years for replacement if the interest rate is 8% per annum and if the sinking fund factor at 8% per annum interest rate for 10 years is 0.069 ?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  The probability of completion of any activity within its expected time is_________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  A tractor shovel has a purchase price of Rs. 4.7 lacs and could save the organization an amount of rupees one lac per year on operating costs. The salvage value after the amortization period is 10% of the purchase price. The capital recovery period will be________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  In the critical path method of construction planning, Free Float can be_____________? Consider the following statements ? 1. greater than Total Float. 2. greater than Independent Float 3. equal to Total Float. 4. less than Independent Float. Of these statements
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  The time corresponding to minimum total project cost is_______________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  During the construction period, price variation clause in contracts caters to__________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Sinking fund is_______________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  In resources levelling________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  PERT is preferred for planning because of________________? Consider the following features/factors 1. Projects are of the non-repetitive type. 2. Time required need not be known. 3. Time required is known precisely. 4. Events have been established for planning. 5. Emphasis is given to activities of project
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  The correct sequence of these operations in tunnel construction is______________? Consider the following operations : 1. Drilling 2. Blasting 3. Mucking 4. Placing steel 5. Placing concrete
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  The maximum rimpull in the first gear of a tractor while towing a load is 6300 kg. The tractor weighs 12.5 tonnes and is operating along a 2 percent upgrade and the rolling resistance is 45 kg/tonne. Pull available for towing the load is________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Which one of the following is not an excavating and moving type of equipment ?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  For excavating utility trenches with precise control of depth, the excavation equipment used is_______________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Batching refers to________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted, and pneumatic tyremounted machines would be respectively_________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Wheeled tractors are replacing crawler tractors because________________? Consider the following statements? 1. wheeled tractors travel faster 2. crawler tractors are more expensive 3. track parts of a crawler wear out quickly 4. crawler tractors have stick control
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Sensitivity analysis is a study of__________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Preliminary project report for a road project must contain___________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts