Construction Planning & Management Mcqs

Q.  In time-cost optimization of a project, crashing is done____________?

a. on all the activities
b. on all the activities lying on the critical path
c. only on activities lying on the orginal critical path and having flatter cost slopes
d. on original critical activities and those that become critical at any stage of crashing in the order of ascending cost slope


ANSWER: See Answer
 
No explanation is available for this question!
MCQs:  The independent float affects only_______________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Free float for any activity is defined as the difference between__________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Total float for any activity is defined as the difference between________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Free float is mainly used to_________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively___________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  In the network shown in Fig. (15 fig) the latest start time of an activity 4-5 is_________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Earliest finish of an activity is always_______________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  In PERT analysis, the time estimates of activities and probability of their occurrence follow_______________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  PERT technique of network analysis is mainly useful for__________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Select the correct statement_______?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Select the incorrect statement_______?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Select the incorrect statement______?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Select the incorrect statement________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  What is defined as the certificate of indebtedness of corporation usually for a period not less than 10 years and guaranteed by a mortgage on certain assets of a corporation ?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Which is NOT an essential element of an ordinary annuity ?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  What is the type of annuity that does not have a fixed time span but continues indefinitely or forever ?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  What is defined as a financial security note issued by business or corporation and by the government as a means of borrowing long-term fund ?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  What is the type of annuity where the first payment does not begin until some later date in the cash flow ?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  What is the type of annuity where the payments are made at the beginning of the each period starting from the first period ?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  What refers to the present worth of all the amount the bondholder will receive through his possession of the bond ?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts