Q.  In PERT analysis, critical path is obtained by joining events having___________________?

a. +ve slack
b. -ve slack
c. zero slack
d. dummy activities
e. critical activities


ANSWER: See Answer
 
No explanation is available for this question!
MCQs:  Bar charts are suitable for_____________________?
Category: Mechanical Engineering Questions,   Published by: T-Code Scripts
MCQs:  In perpetual inventory control, the material is checked as it reaches its__________________?
Category: Mechanical Engineering Questions,   Published by: T-Code Scripts
MCQs:  The reasons which are basically responsible for the formation of a queue should be that ___________________?
Category: Mechanical Engineering Questions,   Published by: T-Code Scripts
MCQs:  In queuing theory, the nature of the waiting situation can be studied and analysed mathematically if_________________?
Category: Mechanical Engineering Questions,   Published by: T-Code Scripts
MCQs:  PERT stands for k (fit) project evaluation and review technique__________________?
Category: Mechanical Engineering Questions,   Published by: T-Code Scripts
MCQs:  PERT is the__________________?
Category: Mechanical Engineering Questions,   Published by: T-Code Scripts
MCQs:  Work study comprises following main techniques_________________?
Category: Mechanical Engineering Questions,   Published by: T-Code Scripts
MCQs:  CPM is the___________________?
Category: Mechanical Engineering Questions,   Published by: T-Code Scripts
MCQs:  PERT and CPM are__________________?
Category: Mechanical Engineering Questions,   Published by: T-Code Scripts
MCQs:  Bin card is used in__________________?
Category: Mechanical Engineering Questions,   Published by: T-Code Scripts
MCQs:  Replacement studies are made on the fol-lowing basis_________________?
Category: Mechanical Engineering Questions,   Published by: T-Code Scripts
MCQs:  Which of the following depreciation system ensures that the interest be charged on the cost of machine asset every year on the book value, but the rate of depreciation every year remains constant_____________________?
Category: Mechanical Engineering Questions,   Published by: T-Code Scripts
MCQs:  The two-bin system is concerned with_________________?
Category: Mechanical Engineering Questions,   Published by: T-Code Scripts
MCQs:  The linear programming techniques can be applied successfully to industries like_________________?
Category: Mechanical Engineering Questions,   Published by: T-Code Scripts
MCQs:  The mathematical technique for finding the best use of limited resources in an optimum manner is known as___________________?
Category: Mechanical Engineering Questions,   Published by: T-Code Scripts
MCQs:  In A-B-C control policy, maximum attention is given to__________________?
Category: Mechanical Engineering Questions,   Published by: T-Code Scripts
MCQs:  According to Rowan plan, if H = hourly rate, A = actual time and S = standard time, then wages will be___________________?
Category: Mechanical Engineering Questions,   Published by: T-Code Scripts
MCQs:  One of the basic essentials of an incentive plan is that_________________?
Category: Mechanical Engineering Questions,   Published by: T-Code Scripts
MCQs:  Which of the following is not wage incentive plan_________________?
Category: Mechanical Engineering Questions,   Published by: T-Code Scripts
MCQs:  Pick up the correct statement from the following?
Category: Mechanical Engineering Questions,   Published by: T-Code Scripts