Construction Planning & Management Mcqs


Q.  If the output of a dragline for 90° angle of swing at optimum depth of cut is X, then the output for 120° angle of swing at 120 % of optimum depth of cut will be_________________?

a. equal to X
b. more than X
c. less than X
d. any of the above


ANSWER: See Answer
 
No explanation is available for this question!
MCQs:  The rated loads of lifting cranes, as percentage of tipping load at specified radius, for crawler-mounted, and pneumatic tyremounted machines would be respectively_________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  Wheeled tractors are replacing crawler tractors because________________? Consider the following statements? 1. wheeled tractors travel faster 2. crawler tractors are more expensive 3. track parts of a crawler wear out quickly 4. crawler tractors have stick control
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  Sensitivity analysis is a study of__________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  Preliminary project report for a road project must contain___________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  The basic action involved in sheep foot rolling is_______________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  The most suitable type of equipment for compaction of cohesive soils is_________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  Grader is used mainly for___________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is__________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  The correct sequence of these activities is________________? Consider the following activities in a building construction? 1. Concreting of roof slabs 2. Brick-jelly lime concrete terracing 3. Erection of form work for slab 4. Construction of parapet wall in terrace
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  The original cost of an equipment is Rs.10,000/-. Its salvage value at the end of its total useful life of five years is Rs. 1,000/-. Its book value at the end of two years of its useful life (as per straight line method of evaluation of depreciation) will be________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  A contractor has two options : Invest his money in project A or (II) : Invest his money in project B. If he decides to invest in A, for every rupee invested, he is assured of doubling his money in ten years. If he decides to invest in B, he is assured of making his money 1.5 times in 5 years. If the contractor values his money at 10% interest rate, he______________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  Mobilization advance up to 10% of the cost of work is given to a contractor_______________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  In time-cost optimization of a project, crashing is done____________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  At a work site, statistical quality control of concrete means________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  In the bar chart planning____________? Consider the following statements? 1. interdependence of the operations cannot be portrayed 2. progress of work can be measured 3. spare time of the activities can be determined 4. schedule cannot be updated
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  If the expected time of completion of a project is 60 weeks with a standard deviation of 5 weeks, the probability of completing the project in 50 weeks and 65 weeks respectively will be__________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  A machine costs Rs. 20000 and its useful life is 8 years. The money is borrowed at 8% interest per annum. The capital recovery factor at 8% interest per annum for 8 years is 0.174. The annual equipment cost of the machine will be________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be__________________?
Category: Civil Engineering Mcqs,   Published by: teswesm
MCQs:  A four wheel trac*or whose operating weight is 12000 kg is pulled along a road having a rising slope of 2% at a uniform speed. Assume grade resistance factor = 10 kg/tonne. The tension in the tow cable is 720 kg. The rolling resistance of the road will be___________________?
Category: Civil Engineering Mcqs,   Published by: teswesm