Q.  How is WINWIN Spiral Model different from Spiral Model ?

a. It defines tasks required to define resources, timelines, and other project related information
b. It defines a set of negotiation activities at the beginning of each pass around the spiral
c. It defines tasks required to assess both technical and management risks
d. It defines tasks required to construct, test, install, and provide user support


ANSWER: See Answer
 
Except option “b” all other tasks/activities are present in Spiral Model as well.
MCQs:  NHPP stands for__________________?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Suitability, Accuracy, Interoperability, and security are what type quality attribute of ISO 9126 ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  What is MTTF ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  How many product quality factors are proposed in McCall quality model ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Which of the following is not a phase of “bathtub curve” of hardware reliability ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  How is software reliability defined ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Time Behavior and Resource Behavior fall under which quality attribute of ISO 9126 ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  The CMM model is a technique to____________________?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Which one of the following is not a software quality model ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  How is reliability and failure intensity related to each other ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Which of the following term describes testing ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  What allows different projects to use the same source files at the same time ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Which of the following is not a change management process ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  How are baselines verified ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Quality also can be looked at in terms of user satisfaction which includes_____________________?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Which of the following is a example of Configuration Items ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  CCB stands for__________________?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Inspections and testing are what kinds of Quality Costs ?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  Quality Management in software engineering is also known as_____________________?
Category: Software Engineering Mcqs,   Published by: teswesm
MCQs:  What information is required to process a change to a baseline ?
Category: Software Engineering Mcqs,   Published by: teswesm