Construction Planning & Management Mcqs

Q.  Grader is used mainly for___________________?

a. trimming and finishing
b. shaping and trimming
c. finishing and shaping
d. finishing, shaping and trimming


ANSWER: See Answer
 
No explanation is available for this question!
MCQs:  The constraints in case of resource smoothening operation would be_______________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Slack time refers to_______________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Economic saving of time results by crashing_________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  The direct cost of a project with respect to normal time is________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  The time with which direct cost does not reduce with the increase in time is known as_________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  What estimate would you give for the variance in above problem ?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  The independent float affects only_______________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Free float for any activity is defined as the difference between__________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Total float for any activity is defined as the difference between________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Free float is mainly used to_________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  If an activity has its optimistic, most likely and pessimistic times as 2, 3 and 7 respectively, then its expected time and variance are respectively___________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  In the network shown in Fig. (15 fig) the latest start time of an activity 4-5 is_________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Earliest finish of an activity is always_______________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  In PERT analysis, the time estimates of activities and probability of their occurrence follow_______________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  PERT technique of network analysis is mainly useful for__________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Select the correct statement_______?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Select the incorrect statement_______?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Select the incorrect statement______?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Select the incorrect statement________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  What is defined as the certificate of indebtedness of corporation usually for a period not less than 10 years and guaranteed by a mortgage on certain assets of a corporation ?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts