Q.  A portion of an embankment having a uniform up-gradient 1 in 500 is circular with radius 1000 m of the centre line. It subtends 180° at the centre. If the height of the bank is 1 m at the lower end, and side slopes 2:1, the earth work involved ?

a. 26,000 m3
b. 26,500 m3
c. 27,000 m3
d. 27,500 m3


ANSWER: See Answer
 
No explanation is available for this question!
TasDia Network - Mcqs | Signature | Lyrics
MCQs:  The damp proof course (D.P.C.) is measured in________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  The volume is measured correct to the nearest__________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  88 is 1400 kg/cm2 and bond stress is 6 kg/cm2, the If tensile stress of a steel rod of diameter required bond length of the rod is____________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Size, capacity and materials need be specified for__________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  The floor area includes the area of the balcony up to_________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  The weight of an item is measured correct to nearest_________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Berms are provided in canals if these are__________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Referring of given figure, pick up the correct statement from the following?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Pick up the incorrect statement from the following _?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Pick up the correct statement from the following __?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Pick up the correct statement from the following ___?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Pick up the correct statement from the following ____?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Pick up the incorrect statement from the following _____?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Pick up the correct statement from the following ______?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Pick up the correct statement in case of water supply ?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Pick up the incorrect statement from the following _______?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  Pick up the incorrect statement from the following?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  The slope of the outlet of ‘P trap’ below the horizontal is kept________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  The expected out turn of half brick partition wall per mason per day is___________________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts
MCQs:  For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is_______________?
Category: Civil Engineering Mcqs,   Published by: T-Code Scripts